Tasks done
88,000
Estimated cost
19,100
Actual spend (budget 185,000)
Antifoul, rig inspection, watermaker membrane change, deck hardware service, generator 7,000 h service.
Tasks + Add task
| Task | Status | Assigned to | Due | Estimate | Actual | |
|---|---|---|---|---|---|---|
| Haul out and pressure wash | Done | Alex Moreno | 17 Nov 2026 | 4,500 | 4,200 | |
| Antifoul and anodes | In progress | Yard | 27 Nov 2026 | 18,000 | ||
| Mast unstep and rig inspection | To do | Rigger | 07 Dec 2026 | 32,000 | ||
| Generator 7,000 h service | To do | Jamie Cole | 17 Dec 2026 | 6,500 | ||
| Watermaker membrane change | Done | Jamie Cole | 27 Dec 2026 | 3,200 | 3,350 | |
| Winch service, all | In progress | Alex Moreno | 06 Jan 2027 | 2,800 | ||
| Teak deck repairs | To do | Yard | 16 Jan 2027 | 21,000 |
Expenses charged to this project + Add expense
| Date | Description | Vendor | Amount |
|---|---|---|---|
| 16 Nov 2026 | Haul out and pressure wash | Refit yard | 4,200 USD |
| 13 Nov 2026 | Watermaker membranes x2 | Marine supplier | 3,350 USD |
| 20 Oct 2026 | Rigging survey deposit | Rigger | 4,000 USD |
| Status | In progress |
|---|---|
| Contractor / yard | Mediterranean refit yard |
| Start date | 28 Oct 2026 |
| Target finish date | 26 Jan 2027 |
| Completed | - |
| Budget | 185,000 |